Oswaldtwistle Civic Theatre will remain closed for at least another six months after roof repairs were delayed again, with no reopening date yet confirmed for the historic venue.
Hyndburn Council has confirmed adverse weather has pushed back the timetable for the building’s roofing works, with the project now expected to continue well into next Spring.
Council leader Cllr Munsif Dad revealed the revised schedule at a meeting of the authority's Full Council on Thursday, November 19, stating the project has been delayed by another six months.
Now, roofing works are set to be completed by April of next year, although the council has factored in additional time for potential weather disruption, giving a provisional completion date of the end of May.
The Civic closed in 2023 and may not open to the public for some time yet (Image: Will Morgan)
However, Cllr Dad stressed the timetable relates only to the roof repairs and that the full reopening of the theatre would still require a full internal refurbishment.
He said: "These dates relate to the roofing works and shall not be interpreted as a confirmed opening date for the theatre."
This latest delay means that residents and community groups, who have been waiting for the venue to reopen since it closed in 2023, may still be waiting this time next year.
Conservative group leader on Hyndburn Council and St Oswalds representative, Cllr Zak Khan, said the authority had “dithered and delayed” over the repairs to the theatre, and he still hadn’t seen a working group set up to oversee the project’s progress.
Conservative group leader and Oswaldtwistle's Councillor Zak Khan slammed the delay (Image: Hyndburn Council)
He said: “They don’t deem it as a priority, and Labour don’t see the Oswaldtwistle Civic as a priority for them.
“If they did, then they’d give it more attention and look at, as I suggested, bringing in more support to get the work done in time.
"If Local Government Reorganisation comes about, how do we know the new authority won’t kick it into the long grass as well?
“We need to get it done now; May and June is too late, we need to bring it forward. The money is there; there’s more money we can spend from reserves, that they’ve managed to find for Accrington.”
The roofing project is being carried out in two phases, with the second stage of lower-level roof repairs expected to begin during the week commencing January 4, 2027.
According to the council, the phased approach will avoid leaving unused scaffolding around the theatre during the Christmas shutdown period, reducing security and safety risks while also cutting the cost of retaining scaffolding on site.
This latest delay marks another setback for the project, which had previously been expected to finish in October of this year. But despite the revised timetable, councillors were told the scheme remains within budget.
A council financial update showed the project had an available budget of £614,750. By the date of the meeting, £163,999.73 had been spent, with a further £213,750.27 committed.
Cllr Dad said that £209,750 of the remaining allocation was earmarked for internal refurbishment works during the 2027/28 financial year.
Read more
Historic mill's plan to save roof and world's last steam-powered weaving shed
Plans for 150 homes on Burnley's outskirts clear environmental hurdle
Derelict Oswaldtwistle warehouse sold off after multiple deliberate fires
He added: "The detailed internal schedule remains to be agreed, with consultation with community groups planned for early 2027."
The theatre, which has served the community for more than 150 years, closed in 2023 after its operating company, Hyndburn Arts Ltd, entered liquidation.
Since then, Hyndburn Council has committed funding towards restoring the building, including repairs to its deteriorating roof.
The latest timetable means the landmark theatre is set to remain closed into a fourth year, with no confirmed reopening date yet in sight.