When it comes to building a 125‑metre bridge across a fast‑flowing river, some elements of the task are bound to prove tougher than others.
As the team working to replace Preston’s Old Tram Bridge has discovered, however, they are not necessarily the ones you might imagine.
Hoisting its four sections into place so that they fit together seamlessly, using one of the biggest cranes in the country? Completed without a hitch.
Drilling deep into the riverbed to install the piers, while abiding by ecological rules to protect the salmon that live in the water? Job done.
Dealing with Preston’s weather patterns? A little more problematic.
Any slight hold‑ups encountered during the near two‑year project can largely be attributed not to the scale of the engineering challenge, but to the city’s propensity for wind and rain.
According to Antony Mulligan, contracts manager for Eric Wright Civil Engineering — the Bamber Bridge‑based firm leading the work — it is the latter that has caused a short delay to the final stages of the £8.2m scheme.
“Since Christmas, we’ve been completing the painting on some of the equipment under the bridge and around the pier structures,” he said. “There were some touch‑up requirements and, typically, they require three or four coats.
“That has admittedly taken longer than we thought, due to the lovely British northern weather. Getting a suitable window to do the work hasn’t been easy in the first quarter of the year.”
When work began in the summer of 2024 to re‑establish the more than 220‑year‑old cross‑river connection between Preston and Penwortham, it was estimated the new bridge could open around the turn of the year. That was later revised to spring.
There is still no confirmed opening date, although Antony said one was likely to be announced by Preston City Council within “the next couple of weeks”. The Local Democracy Reporting Service understands the second half of May is a likely timeframe if the remaining work runs to schedule.
The most significant task still to be completed is resurfacing Old Tram Road, which runs for around a mile from The Cawsey — on the South Ribble side of the bridge — through to the river. The route has been used by construction traffic during the project and the new surface is due to be laid this month.
On the opposite bank of the Ribble, in Avenham Park, Antony said guard rails and handrails are yet to arrive on site but are expected in the coming week.
“They will then start to be installed, and the north side will come together quite quickly after that,” he added.
The bridge’s lighting is already in place and is currently being tested. It will be timed to come on with the lights in the park.
The remaining finishing touches, to be completed over the next month or so, will mark the end of a scheme that will re‑establish the Old Tram Bridge link, first created in 1804. It has had several iterations since, the latest of which was condemned and closed in February 2019 amid fears it could collapse without warning.
Antony said the ease with which that structure was demolished over a fortnight in August 2024 — half the time initially expected — “validated” the decision taken by Lancashire County Council, as highways authority, to close the bridge as soon as its stability was questioned seven years ago.
The fact that weather has been the only real source of delay during construction and installation should not detract from the complexity of delivering the scheme.
For Antony, the biggest combined challenge has been working in a tidal river and reaching the pier furthest from the southern bank, where the works compound has been based.
“We’ve had to mobilise various means of access, including pontoons that didn’t always stand the test of time,” he said. “High rainfall coupled with high tides meant they weren’t always available — and were occasionally seen a bit further downstream.
“We also used man‑riding baskets hooked up to the crane, and at times had two boats to get the team out there so critical work could be completed.
“That certainly wasn’t straightforward. It was something different — we don’t do that kind of work every week — and it was challenging.”
Asked about the most worrying moment of the project, Antony said only one period risked giving him “sleepless nights”: installing the 140 tonnes of new bridge sections and ensuring they fitted together perfectly.
“When there are four sections that have to marry up millimetre‑perfectly to the adjoining substructures and the other sections of the bridge, that is always going to be a testing time.
“But everyone could see how smoothly it went once we got the weather window to carry out the work.”
Read more
Lancashire pub with ‘top quality’ food and new menu up for national award
Best fish and chip towns list snubs Lancashire but locals back this place as a winner
Lancashire walk joining two coastal towns hailed one of the UK’s best for spring 2026
The delicate operation, completed over several days in late November and early December, attracted crowds to the banks of the Ribble. The sight of the work being carried out by a 75‑metre‑high crane, with a jib length of 114 metres, drew visitors from across Lancashire and beyond.
“That shows how much interest there is in the project — not just locally,” Antony said.
The bridge’s designer, John Bridge, said he has also been struck by the public’s fascination with the reinstatement.
“I first did a design almost as an April Fool’s idea in 2020 — a ‘garden bridge’ — but the reaction showed the passion people had for wanting a bridge back there,” he said. “In many ways, it’s a community bridge as well as a physical one.”
He said his firm, Studio John Bridge, has remained closely involved as the final design has taken shape.
“From choosing the colour of the steel to the texture of the concrete and the material of the planks, we’ve been a big part of it. Eric Wright Group have done a fantastic job.”
The real thrill, he added, will come when the bridge is finally in use.
“I can’t wait for everyone to enjoy it. I want to see people, bicycles and a horse going across it on the day it opens,” he laughed.
Given the technical and logistical feat already achieved, arranging an equine presence at the ribbon‑cutting ceremony may well be within reach.